Upper Marsyangdi HEP

 
Contract Details Build Own and operate for 30 years from Plant COD
Expected CoD 2016

 

Himtal Hydro Power Company Pvt. Ltd. is developing ‘The Upper Marsyangdi-2 Hydroelectric Power’ project. This run-of-river type development is located in the districts of Lamjung and Manang, aiming to fully utilize the power potential of the Marsyangdi river.

The proposed location of the dam – utilizing a gross head of about 627.67 m – is just upstream of Tal village (Manang District), about 45 km upstream of Besisahar.

 

More details on the project facilities:

  • 145 m long, 31 m high rockfill dam
  • Discharge capacity of spillway: 4066 m³/second
  • 9.2 km long, horseshoe-shaped headrace tunnel (diameter: 6 m)
  • Underground power house with an installed capacity of 600 MW (four units of 150 MW each)